Item Check Method Maintenance
Interval
Cable
connections
Check that cables are securely
connected.
If clamps are used for AC cable
connections, check that they are
secured with a torque of 35
N·m.
Check that cables are intact, in
particular, the parts touching
the metallic surface are not
scratched.
Check whether the sealing caps
of idle DC input terminals fall
o.
Check that the cover on the USB
port is tightened.
Check that idle RESERVE and
COM waterproof connectors are
plugged and the locking caps
are tightened.
The rst inspection is
half a year after the
initial commissioning.
From then on,
perform the
inspection once six
months to a year.
Grounding
reliability
Check that ground cables are
securely connected.
The rst inspection is
half a year after the
initial commissioning.
From then on,
perform the
inspection once six
months to a year.
8.4 Troubleshooting
Alarm severities are dened as follows:
Major: The inverter is faulty. As a result, the output power decreases or the
grid-tied power generation is stopped.
Minor: Some components are faulty without
aecting the grid-tied power
generation.
Warning: The inverter works properly. The output power decreases or some
authorization functions fail due to external factors.
SUN2000-(90KTL, 95KTL, 100KTL, 105KTL) Series
User Manual
8 Maintenance
Issue 11 (2020-08-30) Copyright © Huawei Technologies Co., Ltd. 99

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei SUN2000-90KTL Series and is the answer not in the manual?

Huawei SUN2000-90KTL Series Specifications

General IconGeneral
BrandHuawei
ModelSUN2000-90KTL Series
CategoryInverter
LanguageEnglish

Related product manuals