The following table outlines the IPL phases from power-on to the AIX login prompt, matching the phases to
corresponding operator-panel checkpoints for a typical system boot. Also listed are the approximate boot
times for each phase, along with their dependencies for each phase.
Note: The following table lists the major checkpoints only.
Phase # Checkpoints on
Operator Panel
Time in phase
(minutes)
Major contributors to time in phase
Phase 1 8xxx => OK Approx. 1
Phase 2 9xxx => 91FF 3 to 6 Number of I/O drawers
Phase 3 Exxx => E105 1 to 3 Number of bootable adapters
Phase 4 0xxx => blank 2 to 30+ Number of SSA drives
Number of SCSI drives
Number of Async sessions
Number of processors
Number of adapters
Amount of memory
136 Service Guide

Table of Contents

Other manuals for IBM RS/6000 Enterprise Server M80

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IBM RS/6000 Enterprise Server M80 and is the answer not in the manual?

IBM RS/6000 Enterprise Server M80 Specifications

General IconGeneral
BrandIBM
ModelRS/6000 Enterprise Server M80
CategoryServer
LanguageEnglish

Related product manuals