INSTALLATION
Ideal Logic Code Combi - Installation and Servicing
WARNING.
Whilst effecting the required gas tightness test and purging air from the gas installation,
open all windows and doors, extinguish naked lights and DO NOT SMOKE.
A. Electrical Installation
1. Checks to ensure electrical safety should be carried out by a

2. carry out the preliminary electrical system checks,


B. Gas Installation
1. 
should be inspected and tested for tightness and purged in


2. 

37
COMMISSIONING AND TESTING
GENERAL
Please Note
been checked, adjusted and preset at the factory for


DO NOT 
Having checked:
 

 


CHECK THE OPERATIONAL (WORKING) GAS
INLET PRESSURE

opening hot tap to maximum

With the boiler operating in
the maximum rate condition
check that the operational
(working) gas pressure at
the inlet gas pressure test
point complies with the


Ensure that this inlet pressure
can be obtained with all other
gas appliances in the property

Safety
Drain
Valve
Black
Handle
Yellow
Handle
Black
Handle
Blue
Handle
3G9927
CH Flow
DHW Outlet
Gas Supply
CH Return
DHW Inlet
Gas Pressure
Test Point
ATTENTION !
IT IS A CONDITION OF THE MANUFACTURERS WARRANTY THAT THE
BENCHMARK COMMISSIONING CHECKLIST IS FULLY COMPLETED
AND LEFT WITH THE APPLIANCE
INSTALLATION
206279-1.indd 32 06/01/2011 09:10:21