Single Phase Hybrid Inverter Commissioning
25
Chapter 6 Commissioning
6.1 Startup
Step 1: Close the AC circuit breaker of the inverter at GRID side.
Step 2: Close the DC circuit breaker of the inverter at BAT side.
Step 3: Close the AC circuit breaker of the inverter at EPS side.
Step 4: Turn on the PV switch of the inverter.
Note: the system will work in On Grid state upon normal connections at PV side, GRID side and BAT side.
The green LED will remain on, and the message “State: On Grid” will appear on the screen of the hybrid
inverter.
6.2 Shutdown
To stop the operation of the hybrid inverter, please disconnect all energy sources to enter automatic shutdown.
Step 1: Turn off the PV switch.
Step 2: Turn off the BAT switch.
Step 3: Disconnect the power grid.
Both the LED light and LCD screen will be turned off.
Note: At the end of the above steps, please wait at least 5 minutes before proceeding to other operations.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the INVT XD Series and is the answer not in the manual?

INVT XD Series Specifications

General IconGeneral
BrandINVT
ModelXD Series
CategoryInverter
LanguageEnglish

Related product manuals