Position cylinders 1 and 6 at TDC.
Fit tool 99368509 (3) on the front casing.Secure it using the
bolts (2, 5).
At TDC the pins (2) and (3) for the tool engage in the dowels
for the crankshaft and the camshaft respectively guaranteeing
the timing.
With tool 99368509 (3, Figure 48) fitted, fit the two timing
gears (6) and the spacer (5) and secure the assembly using the
bolts (4).
Fit the tool (1) 99368508 on the front casing as shown in the
diagram.
Fit the flywheel (2) so that the tool 99368508 is inserted, via
the seat for the timing sensor, on the tooth on the flywheel
(see arrow).
Proceed with tightening the bolts (3).
113064
113065
Method 2 (using equipment)
Flywheel timing
SECTION 4 - OVERHAUL AND TECHNICAL SPECIFICATIONS 27
VECTOR 8 ENGINES
Print P2D32V001E Base - April 2006

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Iveco VECTOR Series and is the answer not in the manual?

Iveco VECTOR Series Specifications

General IconGeneral
BrandIveco
ModelVECTOR Series
CategoryEngine
LanguageEnglish

Related product manuals