KBR multicomp F144-NC-1V1C6DO6RO-2Commissioning
4.2 Compensation system with controller
The controller is preset as a component of a compensation system (refer to the
connection diagram of the compensation system). The following need to be
programmed or checked:
Target CosPhi according to energy supplier regulations.
Primary and secondary current in the main circuit according to the mounted
transformer.
If required, set the measuring voltage transformer data.
If no stage powers have been programmed, the controller will switch to the
Commissioning menu. Subsequently, the stage power can be programmed in
the settings menu, or using the learning process.
The programmed values are saved on an EEPROM and will thus not be lost
after a mains failure.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the KBR multicomp F144-NC-1V1C6DO6RO-2 and is the answer not in the manual?

KBR multicomp F144-NC-1V1C6DO6RO-2 Specifications

General IconGeneral
BrandKBR
Modelmulticomp F144-NC-1V1C6DO6RO-2
CategoryController
LanguageEnglish

Related product manuals