6 Installation at Site
15 of 44
Hya-Solo DSV
NOTE
In order to avoid transmission of piping forces onto the pressure booster system
and transmission of solid-borne noise, we recommend installing length-limited
expansion joints.
Allow sufficient space for maintenance and repair work.
ü All structural work required has been checked.
ü The dimensions of the concrete foundation are correct, and the concrete has set
firmly.
1. Mark out the anchoring holes on the floor as shown in the outline drawing.
2. Drill the holes (max. diameter: 12mm).
3. Insert plug fixings of appropriate size.
4. Set the pressure booster system down in its correct installation position.
5. Use suitable bolts to firmly anchor the pressure booster system.
6.4 Installing the piping
Make sure that piping is installed without transmitting any stresses or strains. The use
of length-limited expansion joints (see accessories) is recommended.
CAUTION
Air pockets in suction line
Pressure booster system cannot prime!
▷ Lay piping with a continuously rising slope (as shown).
Suction lift operation
Incorrect Correct
NOTE
For suction lift operation install suitable swing check valves at the suction line ends
which are submerged in the fluid handled. Take into account the head losses
caused by these swing check valves.
Do not exceed the maximum suction lift of the pumps.
6.4.1 Fitting an expansion joint
DANGER
Sparks and radiant heat
Fire hazard!
▷ Take suitable precautions to protect the expansion joint if any welding work is
carried out nearby.