n For calibration, the reference thermometer must be installed in the
inlet of the device according to the specifications on the calibration
certificate.
n To measure the temperature, wait until the system is in a steady state.
1. Press the [Enter key] to open the menu.
2.
Select the menu items Setup Calibration intern Pt1000 or
extern Pt100 Oset.
The entry window opens.
3. Enter the temperature value read from the reference thermometer
into the entry window.
4. Press the [OK] to confirm the new value.
The new value has been accepted.
n For calibration, the reference thermometer must be installed in the
inlet of the device according to the specifications on the calibration
certificate.
n The upper and lower temperature measurement points must be at least
40 K apart.
n To measure the temperature, wait until the system is in a steady state.
1. Set a low T
set
setpoint on the device.
2. Wait until the setpoint and the temperature of the heat transfer liquid
have equaled out.
3. Press the [Enter key] to open the menu.
4.
Select the menu items Setup Calibration intern Pt1000 or
extern Pt100 2-point lower .
The entry window opens.
5. Enter the temperature value read from the reference thermometer
into the entry window.
6. Press the [OK] to confirm the new value.
The lower value has been accepted.
7. Set a high T
set
setpoint on the device.
8. Wait until the setpoint and the temperature of the heat transfer liquid
have equaled out.
9. Select the menu item [2-point upper] in the Calibration menu.
The entry window opens.
10. Enter the temperature value read from the reference thermometer
into the entry window.
11. Press the [OK] to confirm the new value.
The upper value has been accepted. 2-point calibration has been
completed.
Oset
2-point calibration
V6 Integral Process Thermostats and High-Temperature Thermostats 103 / 198