3-phase mains connecon 400 V
Connecon diagrams
A mains choke is required for the oper
aon of inverters ≥ 15 KW.
The c
onnecon plan is valid for the inverters I95AExxxF.
X257
X256
PROFINET
X267
X266
EtherNet/IP
X247
OUT
X246
IN
EtherCAT
X237
OUT
X236
IN
On-board
EtherCAT
X16
Engineering-Port
X83
X82
X1
n
EYF
GB
24B
DC 24 V SELV/PELV
(+19.2 V ... +28.8 V)
BD2
BD1
DC 24 V SELV/PELV
(+19.2 V ... +28.8 V)
DC 24 V SELV/PELV
(+19.2 V ... +28.8 V)
X3
GO
DO1
24O
GI
DI1
DI2
DI3
DI4
AI1-
AI1+
DC 24 V SELV/PELV
(+19.2 V ... +28.8 V)
3/N/PE AC 400 V
3/PE
AC 340 V ... 528 V
45 Hz ... 65 Hz
Fig. 13: Wiring example
S1 Start/stop
Fx
Fuses
Q1 Mains contactor
EYF Lenze system cable
--- Dashed line = opons
A c
onnecon diagram for the terminal X1 can be found under: 4Basic Safety - STO ^ 167
Electrical ins
tallaon
Mains connecon
3-phase mains connecon 400 V
142