Operation
Sequence Of Operation
Initial Start-Up
PRIMING WATER SYSTEM
Models built July 2010 or later:
Place the toggle switch in the wash/fill position, the
water fill valve and water pump energize. Wait 90
seconds for the water system to fill, then place the
toggle switch in the ice position.
Models built before July 2010:
The water inlet valve energizes in the harvest
sequence, therefore priming the system with water will
allow the system to start up with a full reservoir of
water. To prime system, remove water curtain, and
add 2 liters of water into the water trough.
Continued Next Page