9 - 28
CHAPTER9 DEVICES
9
9.2 Internal User Devices
9.2.10 Timer (T)
(7) Timer processing and accuracy
(a) Processing
When the OUT T or OUT ST instruction is executed, the on/off switching of the timer coil, current value
update, and on/off switching of the contact are performed.
In the END processing, the current timer value is not updated and the contact is not turned on/off.
Figure 9.24 Processing at execution of the OUT T0 instruction
X0
T0
K10
END OUT TO END
[Processing at execution of OUT T0 instruction]
[Ladder example]
Sequence
program
Processing
Coil ON/OFF
Current value update
Contact ON/OFF

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Mitsubishi 00JCPU and is the answer not in the manual?

Mitsubishi 00JCPU Specifications

General IconGeneral
BrandMitsubishi
Model00JCPU
CategoryController
LanguageEnglish

Related product manuals