Commissioning
- 37 -
optek-Manual--1004-1022-02--156-US-2017-12-11
www.optek.com
9.8 Other activities when commissioning
1. Check the system zero point of the converter (see chapter 9.4, page 31).
2. Check the set measuring range (see chapter 9.5, page 32).
3. Check the set alarm limit values (see chapter 9.6, page 35).
4. Document your settings using the form (see chapter 12.1, page 43).
5. Check measuring results with regard to plausibility.
6. If settings and measuring results are correct, enable measuring.