Operation
62 / 89
Operation
System supply
The power generator is in system supply mode and functions like an
earthed TN network. This corresponds to a power supply from a transform-
er to a building. The 400 V CEE supply socket (white, 1 o'clock position) is
supplied with voltage. The neutral conductor and the earth of the power
generator are connected. The outer conductors and the neutral conductors
of the direct, front-side sockets are physically separated from the generator.
The ISO monitor is deactivated. With system supply no electrical consum-
ers may be connected to the front sockets.
Changeover position
► Switch the Direct supply/building feed switch to Position 0.
All sockets on the power generator are de-energised.
Changeover position
All outer conductors and all neutral conductors are physically separated
from the generator.
0
12