Installation
5.2 Preparation for installation
Valve and actuator can be assembled before
or after the valve has been installed in the
pipeline.Werecommendrstinstallingthe
valve without the actuator into the pipeline.
Beforeinstallation,makesurethefollowing
conditions are met:
− The valve is clean.
− The valve, actuator and all piping are
not damaged.
− Install a strainer upstream of the regula-
tor.
− The valve data on the nameplate (type
designation,valvesize,material,pres-
sure rating and temperature range)
matchtheplantconditions(sizeand
pressure rating of the pipeline, medium
temperature etc.). See the 'Markings on
the device' section for nameplate details.
− Therequestedorrequiredadditionalt-
tings (see the 'Design and principle of
operation' section) have been installed or
prepared as necessary before installing
the valve.
Proceed as follows:
Î Lay out the necessary material and tools
to have them ready during installation
work.
Î Flush the pipeline before installing the
regulator.
The plant operator is responsible for
cleaning the pipelines in the plant.
Î For steam applications, dry the pipelines.
Moisture will damage the inside of the
regulator.
Î Check any mounted pressure gauges to
make sure they function properly.