Servicing and maintenance
6.4 Standard commissioning
CU240S and CU240E Control Units, FW 3.2
218 Operating Instructions, 03/2009, A5E02440075B AA
6.4 Standard commissioning
Standard commissioning with a valid parameter set
If you have a memory card with a valid parameter set, then you can also perform standard
commissioning for several inverters.
Prerequisites
Several inverters (Control Units and Power Modules of the same type) must be
commissioned for the same application.
A memory card with a valid parameter set is available.
Procedure for standard commissioning
1. Insert the memory card into the control unit of the first inverter.
2. Switch-on the inverter power supply (the valid parameter set is downloaded into the
inverter from the memory card)
3. Wait until the inverter has completely booted (RDY-LED and SF-LED are lit, BOP returns
to the standard display)
4. Remove the memory card and acknowledge message F0395 (SF-LED is dark)
5. Proceed with the next inverter