This section contains information about the commissioning of the 7SR46 device. Test functions in the device
support you during testing, simplify testing processes, and reduce testing times.
The secondary test is used for checking:
•
Correct setting of functions
•
Routing of logical signals to the binary inputs and outputs
•
Interfaces and many more
You can find the offline testing options during engineering in the Reydisp Evolution online help.
Commissioning Notes
The commissioning tests are carried out to prove the following:
•
The relay is not damaged in transit
•
The relay is correctly connected and installed
•
The characteristics of the protection and settings which are based on calculations
•
Settings are correctly applied
•
Obtain a set of test results for future reference