Testing Readiness for Operation
By carrying out the points in 7.4 Initial Startup. The device is ready for operation. If devices are built into cabi-
nets, additional wiring and communication connections are necessary.
Siemens recommends the following procedure in this order:
Testing Binary Inputs, Binary Outputs and External Trip Input
Check that the connection from the output of the testing equipment to the device is correct and the binary
inputs, binary outputs and external trip input are connected correctly.
Testing Current Inputs
Using multi-phase test equipment, apply the corresponding test quantities and check the results.
Testing Protection Functions
The purpose of this test is to verify the correct setting of protection functions and the routing of signals. To do
this, you can feed the test signals with test equipment. Digital test equipment offers you multiple test
programs and test sequences.
Output Test
The relay fascia displays the output test feature and allows you to operate the relays functions. The output test
of the selected function automatically operates the binary output assigned to that function. The output test
displays any enabled protection function in the setting menu.
7.6
Commissioning
7.6 Testing Readiness for Operation