CP 1243-1 DNP3, CP 1243-1 IEC
Operating Instructions, 02/2014, C79000-G8976-C312-02
17
The following setups do not take into account rails, housing, cabling and other accessories.
Depending on the configuration of your plant, you require the following devices and firmware
versions.
Application example: Project with 1 subnet
The following setup assumes that the master and stations are located in 1 IP subnet, see
also the section Configuration with 1 subnet (Page 14).
●
– When using a DNP3 CP with firmware version V1.0: A CPU with firmware version
V3.0.
– When using a DNP3 CP with firmware version V1.1: A CPU with firmware version
V3.0 or V4.0.
●
– IEC CP
– CPU with firmware version V3.0 or V4.0
● PC for compatible DNP3 or IEC master
With redundantly designed master stations, the hardware needs to be doubled.
● When using online functions: Engineering station with STEP 7 (see following section)
Application example: Distributed project connections over the Internet
In the remote S7-1200 station:
The following set up assumes that the master and stations communicate via the Internet, see
also the section Configuration with connections over the Internet (Page 14).
●
– When using a DNP3 CP with firmware version V1.0: A CPU with firmware version
V3.0.
– When using a DNP3 CP with firmware version V1.1: A CPU with firmware version
V3.0 or V4.0.
– DSL router + SCALANCE S
See also the reference in the section "Notes on the DSL router" below.