Commissioning (software)
7
7.1 Overview of commissioning
7.1.1
Requirements for commissioning
The requirements for commissioning the SIMOTION D410-2 are as follows:
The system has been connected and wired.
The SIMOTION D410-2 is switched on and powered up (STOP operating state).
SIMOTION SCOUT (with integrated STARTER) has been installed and started on the PG/
PC.
Communication between the SIMOTION D410-2 and the PG/PC is configured.
You have created a project and installed a SIMOTION D410-2 in the project.
7.1.2 Symbolic assignment / adaptation
Symbolic assignment
SIMOTION supports the symbolic assignment on SINAMICS drive objects (DOs) during the
configuration of technology objects (TOs) and I/Os.
This simplifies the configuration of the technological relationships including the communication
between controller and drive.
With the symbolic assignment:
Only suitable assignment partners are offered in an assignment dialog box.
Communication between axis and drive is set up automatically by the engineering system
and the required PROFIdrive axis telegrams as well as the used addresses set up.
Telegrams are extended and interconnections created automatically in the drive depending
on the selected TO technology (e.g. SINAMICS Safety Integrated).
Axis and drive configuration are first performed independently.
Communication connections are established automatically during the configuration of I/O
variables on SINAMICS I/Os (telegrams are set up automatically, the I/Os interconnected
to the telegram and the addresses set up).
SIMOTION D410-2