Procedure
To end the System Interface Test, click on &ORVH. The device is briefly out of service
while the start-up routine is executed. The dialog box closes.
Note:
When the System Interface Test is terminated, the device changes to the start-up
mode (reboots). All hardware components are returned to the operating conditions de-
termined by the substation settings; however, all message buffers are deleted. Any
data required from the message buffers must therefore be read before the test is
closed.