Building Technologies Basic documentation: Communication via the KNX bus CE1P3127en
HVAC Products Appendix 30.08.2007
9.2 Heating / cooling changeover
The universal RMU7x0B controllers are programmed with the new "H/C
changeover" function block, which is used for changeover of the specified
"Heating" or "Cooling" mode in 2-pipe systems.
x
H/C changeover
Q
23
The specified "Heating" or "Cooling" mode can be generated in the controller itself,
or received as a "Heating/cooling changeover signal" over the KNX bus.
The following methods of changeover can be programmed for the specified
"Heating/Cooling" mode:
Changeover via digital input, e.g. with manual switch or with a changeover
thermostat in the flow (already an option with RMU7x0).
Changeover vie analog input, e.g. based on outside air temperature or flow
temperature.
Changeover based on the calendar (date): Configured in the "H/C Changeover"
function block (calendar symbol checkbox selected)
Changeover with operating mode selector. Configured in the "H/C Changeover"
function block ("Hand" symbol checkbox selected)
The "Heating/Cooling" mode is not affected by the type of changeover.
If several types of changeover are selected, the required operating mode is
determined in the following order of priority:
1. Operating mode selector
2. H/C changeover input
3. Heating/cooling based on calendar
The required "Heating/Cooling" mode is transmitted by the "changeover controller"
to all other controllers in the heating distribution and refrigeration distribution zones.
In a hydraulic circuit, the "Heating/Cooling" mode can be defined in one location
only. If several H/C changeover signals in the same distribution zone are
distributed over the KNX bus, a fault message is generated.
If possible, the required "Heating/Cooling" changeover command should be
activated in the primary controller or generator.
The "H/C changeover" function is activated by setting the operating line "2-pipe
system heating/cooling" to "Yes".
Main menu > Commissioning > Extra configuration > Heating/cooling changeover
Operating line Range Factory setting
2-pipe heating/cooling system No, Yes No
Use
Effect of specified mode
Note
Activating the function
Configuration

Table of Contents