Section 4 – Inspections Before Operation
4.1 Operator’s responsibility
Do these tasks before each work shift and in this
sequence:
1. Visual and daily maintenance inspections
(refer to Section 4.2).
WARNING
Do an inspection on the MEWP for damage or
loose or missing parts. If damage is found, lock
and tag the MEWP and remove it from service. If
you do not obey, there is a risk of death or serious
injury.
2. Function tests (refer to Section 4.3).
Refer to Section 4.4 for a checklist of the inspection
items.
WARNING
If the MEWP is damaged or has been modied
from the initial factory-delivered condition, without
permission from Skyjack, lock and tag the MEWP.
Remove the MEWP from service. If you do not
obey, there is a risk of death or serious injury.
Repairs to the MEWP are tasks only for a qualied
service technician. Do the visual and daily
maintenance inspections and function tests again
after the repairs.
Scheduled maintenance inspections are a task only
for a qualied service technician.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Skyjack SJ46 AJ and is the answer not in the manual?

Skyjack SJ46 AJ Specifications

General IconGeneral
BrandSkyjack
ModelSJ46 AJ
CategoryLifting Systems
LanguageEnglish

Related product manuals