EasyManua.ls Logo

Skyjack SJ85 AJ - Testing Start;Function Enable;Emergency Power Switch and All Boom and Platform Functions; Testing Platform Self-Leveling

Skyjack SJ85 AJ
112 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
213217AAA SJ85 AJ
50
Section 4 – Pre-operation Function Tests
4.3-4 Testing start/function enable/
emergency power switch and all
boom and platform functions
WARNING
Ensure that there are no personnel or obstructions
in test area and there is sufcient room for boom
to swing.
1. Ensure emergency stop button is pulled out.
2. Start engine.
3. Do not hold start/function enable/emergency
power switch in function enable position.
Attempt to activate each boom and platform
switch.
Result: All boom and platform functions
should not operate.
4. Hold start/function enable/emergency power
switch in function enable position and activate
each boom and platform function.
Result: Engine speed increases from idle to
intermediate. All boom and platform functions
should operate as selected.
4.3-5 Testing platform self-leveling
1. Lower boom to stowed position.
2. Adjust platform to a level position using platform
leveling switch, which controls
tilting up or tilting down of platform.
3. Fully raise main boom.
Result: Platform should remain level at all
times and lifting speed should slow down
before boom reaches full height.
4. Fully lower main boom.
Result: Platform should remain level at all
times.
TM
HOUR METER
QUARTZ
Base control console
Start/function enable/
emergency power switch
Off/base/platform key
switch
Emergency stop

Table of Contents

Other manuals for Skyjack SJ85 AJ

Related product manuals