SMA Technologie AG (First) Commissioning
Technical Description SI5048-11:EE4206 Page 59
System configuration overview:
Displayed text Meaning
1phase 1SI PV 1-phase system, 1 Sunny Island 5048, photovoltaics only
1phase 1SI OG 1-phase system, 1 Sunny Island 5048, offgrid + generator
1phase 1SI GB 1-phase system, 1 Sunny Island 5048, backup on the grid
1phase 2SI PV 1-phase system, 2 Sunny Island 5048 devices, photovoltaics only
1phase 2SI OG 1-phase system, 2 Sunny Island 5048 devices, offgrid + generator
1phase 2SI GB 1-phase system, 2 Sunny Island 5048 devices, backup on the grid
1phase 3SI PV 1-phase system, 3 Sunny Island 5048 devices, photovoltaics only
1phase 3SI OG 1-phase system, 3 Sunny Island 5048 devices, offgrid + generator
1phase 3SI GB 1-phase system, 3 Sunny Island 5048 devices, backup on the grid
1phase 4SI PV 1-phase system, 4 Sunny Island 5048 devices, photovoltaics only
1phase 4SI OG 1-phase system, 4 Sunny Island 5048 devices, offgrid + generator
1phase 4SI GB 1-phase system, 4 Sunny Island 5048 devices, backup on the grid
Three 3SI PV 3-phase system, 3 Sunny Island 5048 devices, photovoltaics only
Three 3SI OG 3-phase system, 3 Sunny Island 5048 devices, offgrid + generator
Three 3SI GB 3-phase system, 3 Sunny Island 5048 devices, backup on the grid
If you have a system with more than one Sunny Island 5048 device, you must first
run the QCG on the slave(s) before starting the master device (display message
"INIT MASTER OK START?"). Only the device type is set there. Only start the
master device thereafter!
If the "New Battery" option is selected, only specific battery settings are reset and
set to new values. System settings are not affected.
7. After entering the parameters listed below, the display
of the master shows the following message:
8. Press <ENTER> to confirm. The following message then
appears on the display.
9. Press <ENTER>. A beep is heard, the Sunny Island 5048 starts and is operating.
The green (upper) LED is illuminated.
INIT MASTER OK
START? ↵
Standby-To start
press <ENTER>