7 Commissioning SMA Solar Technology AG
80 SI80H-60H-OffGrid-IA-en-11 Installation Manual
10. Setting a single-phase or three-phase off-grid system:
Select the 003.15 ClstType parameter and
press the button.
For a single-phase off-grid system, set 1Phs and press the button.
For a three-phase off-grid system, set 3Phs and press the button.
Confirm the off-grid system with Y.
11. Setting single-cluster operation for a three-phase off-grid system:
Select the 003.16 Sys parameter and press the
button.
•Set SingleClst and press the button.
Confirm single-cluster operation with Y.
12. Setting the external energy source:
Select the 003.20 ExtSrc parameter and press
the button.
For an off-grid system without an external energy source, set PvOnly and press the button.
For an off-grid system with a generator, set Gen and press the button.
For an off-grid system with the electricity grid as external energy source, set Grid and press
the button.
For an off-grid system with a combination of electricity grid and generator, set GenGrid and
press the button.
Confirm the external energy source with Y.