EasyManua.ls Logo

SMA SUNNY TRIPOWER X 20-US - Commissioning; Procedure for Commissioning as System Manager

SMA SUNNY TRIPOWER X 20-US
104 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
7 Commissioning
SMA Solar Technology AG
Operating manualSTPxx-US-50-BE-en-1154
7 Commissioning
7.1 Procedure for commissioning as SystemManager
This section describes the procedure of commissioning an inverter that is used in systems with
SystemManager.
It provides an overview of the steps, which must be performed in the prescribed sequence.
Procedure See
1. Commission all SMA Speedwire devices
that are to be subordinate to the System
Manager (e.g., inverters, energy meters).
Manual of the devices
2. Commission the inverter. Section7.3, page55
3. Establish a connection to the user interface
of the inverter. There are various connec-
tion options to choose from for this:
Direct connection via Wi-Fi
Connection via WLAN in the local
network
Connection via Ethernet in the local
network
Section8.1.2, page59
Section8.1.1, page57
4. If required, change the network configura-
tion on the welcome page. The automatic
network configuration recommended by
SMA Solar Technology AG via DHCP
server is activated by default. Only change
the network configurations if the default
configuration is not suitable for your net-
work.
Commissioning Assistant
5. Carry out the configuration using the Com-
missioning Assistant. Select Inverter as
System Manager in the device configura-
tion.
Commissioning Assistant
6. To monitor the system in the Sunny Portal
and view the data visually, create a user
account in the Sunny Portal and create a
system in the Sunny Portal or add devices
to an existing system.
https://ennexOS.SunnyPor-
tal.com
Also see:
Device Configuration⇒page19

Table of Contents

Other manuals for SMA SUNNY TRIPOWER X 20-US

Related product manuals