5.5.2 Installation of liquid cooling pipelines during cabinet consolidation
The installation of liquid cooling pipelines only involves on-site installation when the energy
storage main cabinet is combined with the battery cabinet or when the battery cabinet is combined
with the battery cabinet. If the energy storage main cabinet is used separately, it does not involve the
installation of liquid cooling pipelines for cabinet integration. The installation of the liquid cooling
pipeline for the cabinet includes four steps: removing the side pipe cover plate of the cabinet, opening
the sealing groove, installing the pipeline, and closing the sealing groove.
Step 1: Open the sealing slot. Open the two sealing slots between two parallel cabinets, use a
screwdriver to remove four M4 screws, and rotate the sealing slots 45 degrees upwards to open them.
Figure 5.15 Disassembling the sealing slot screws
Figure 5.16 Flipping and opening the sealing slot
Step 2: Install the pipeline. Loosen the clamp at the end of the liquid cooling pipeline of the two