Decommissioning
9 — 1
10_0036_0802GB
9 Decommissioning
This chapter contains information on decommissioning the machine.
I
f the machine is to be shut down temporarily, take the following
measures.
" Terminate delivery. Refer also to chapter: ”Operation” -- section:
”Operating the machine”.
" Switch off the machine. Refer also to chapter:
”Starting up” -- section: ”Shutting down the machine after
starting up”.
" Actuate the pneumatic tool until the air hose is completely
depressurised.
Danger
Only disconnect the air hose when you are certain that the system is
depressurised.
" Detach the air hose.
" Disconnect the machine from the mains.
" Drain the condensate water.
Maintenance chart: Draining condensate water.
" Clean the machine. Refer also to the chapter:
”Operation” -- section: ”Cleaning the machine”.
" Shut down the machine only in current-free condition.
9.1 Temporary
de
commissioning