Chapter 2: Installation
2-5
2-3 Installation of the Universal Retention
Mechanism (URM)*
Please Note! Screws and washers attach from the bottom of the
board and must be installed before mounting the board to the
chassis. (See Figures 2-4 and 2-5.)
1. When installing the URM, be sure the
Left
(L) and
Right
(R) sides are
placed accordingly.**
2. Lift both arms upright and slide the processor into the socket, noting that
the notches need to line up.
*These directions may not apply to second source URMs
** Newer URMs are not left/right specific. Also, caps are only needed for SECC2 cartridges.
2-4 Special Instructions for the Celeron Processor
Please Note! The Celeron processor requires special caps to hold
it in place (these caps are bundled with the motherboard). (See
Figures 2-4 and 2-5.)
1. Lift both URM arms to their upright positions.
2. Slide the Celeron processor into the socket making sure that the
notches line up.
3. Slide the special Celeron caps over the ends of the retention arms.
Make sure the arrows face outward and that the
Left
(L) and
Right
(R)
caps are on the appropriate sides of the URM. The caps should snap
into place.
4. To remove the caps, pull out on the tab (arrows points to tab) and
then pull up.