INITIAL BREAK-IN
With all new mechanical equipment, a certain break-in period is required to allow components and mechanical devices to
seat and mesh properly.
Supreme International recommends the following items be completed at the prescribed time lines in order to fully take
advantage of Supreme International’s reputation for strength and reliability. For maintenance intervals, see
36.
After the rst 10 hours of operations After the rst 100 hours of operations
• Check and tighten all fasteners holding the knives on
the auger (see
38 and
39)
• Visually inspect oil lines and hydraulic lines for leaks.
• Check and tighten scale head-swivel adjustment knob.
• Grease all driveline components with two pumps
(except gearboxes) as shown in
37.
• Change oil in all pump drives, and gearboxes to
after initial break-in.