| Start-up, adjustments, use, commissioning and unit in hipernation
• Damper motors
• Filter guards
• Temperature sensors
• Fire thermostats
• Smoke detectors
• Pressure transmitters
• Valves
• Valve motors
• Humidity sensors
• CO2 sensor
• Control panel
• Humidifier
• E-Tool software for fast communication with the Corrigo controller
• Other
K.3 Documentation is available for download
from https://techdoc.systemair.dk
Your local Systemair company is able to provide the data.
K.4 Start-up by installer
All protection and safety measures must be met before start-up of the unit. The mains supply voltage must also be
checked too. The mains supply voltage must be measured at the supply terminals in the cabinet.
K.4.1 Checklist, relevant values
K.4.1.1 Checklist prior to start-up
• Is the unit assembled correctly with its functions in the correct order? See Annex 2.
• Are the sections and ducts assembled correct? See annex i.
• Check that fans and anti-vibration mounts are not damaged after transportation and installation.
• Is the rotary exchanger turning freely?
• Are safety guards installed correctly?
• If the unit includes integrated heat pump, check whether it is installed and supervised by qualified service personnel.
• If the unit contains Electric air heater, make sure that the supply isolator disconnects with the unit.
• Ducts - are all ducts installed?
• External components - are the valve and valve motor installed correctly?
• Is the circulation pump installed correctly?
• Is water under pressure in the coil and circulation pump?
• Are the pressure transmitters installed and connected correctly? (If this is a system with pressure transmitters in the
ducts)
• Main power supply:
• Connected correctly? (3x400 V + N + PE)
• Test of supply voltage for actuators and control signal!
• Are control signals for actuators connected correctly?
K.4.1.2 Switch on power
Warning
Do not start until all safety procedures have been completed and ensure that inspection doors are closed
and locked.
output |