Inspect Your Ins
trument
3. Click Run. The test results appear in the
diagnostics control window.
4. Verify that all tests pass. If diagnostic
failures occur
, contact your local
Tektronix service personnel.
Signal Path Compensation
Use this procedure if the temperature has changed more than 5 °C (9 °F) since the last signal path compensation.
Perform the signal path compensation once a week. Failure to do so may result in the instrument not meeting warranted
performance levels.
1. Prerequisites: instrument powered on
for 20 minutes, and all input signals
removed.
2. Select Instrument Calibration .