IBUC Operation Manual
Terrasat Communications Inc.
Rev. A
4-1
Chapter 4 IBUC Systems: Installation &
Setup
______________________________________________________________________
The Terrasat ODU consists of an IBUC, and could include an LNB, a PSUI and a set of
interconnection cables. The Terrasat IDU consists of an IFU.
This section contains the general requirements for installation of the ODU to the
antenna and the IDU between the Modem and the ODU.
WARNING:
- FOR PROTECTION OF PERSONNEL AND EQUIPMENT, USE CARE
WHEN INSTALLING THE ANTENNA AND WHENEVER WORKING ON
OR AROUND THE SYSTEM.
- TAKE STANDARD SAFETY PRECAUTIONS WITH HAND AND/OR
POWER TOOLS.
- USE CARE IN WORKING WITH DANGEROUS VOLTAGES.
Unpacking
Check to make sure that the ODU has not suffered damage in shipment. If damage is
noticed contact Terrasat customer support.
Compare the contents of the shipping container with the packing list to ensure all items
have been received. If any item is determined to be missing contact Terrasat customer
support.
Retain all shipping containers for future use.
Installing the Outdoor Unit (ODU)
Tools and Test Equipment
Have on hand a standard electrician's tool kit and any tools listed in the antenna
manufacturer's installation instructions.
Site Considerations
The ODU is designed to mount on the antenna. Locate and install the antenna
according to instructions supplied by the antenna manufacturer. Choose an area that is
free of extraneous interference from motors and electrical equipment and has a clear