VOLLMER WERKE
Operating instructions
Issue: 01
MAP 200 / 400
Page: 6-3
Grease all unpainted parts lightly after removing the rust protection agent.
6.6 Installing the machine
The installation site must conform to the conditions specified in the chapter “Requirements at the in-
stallation site“.
Note
The securing elements used to prevent the machine from shifting during transpor-
tation must not be removed until the machine has reached its final destination.
6.6.1 Fix the machine to the floor
These machines are equipped with drillings for mounting with screws. The distance between the bore-
holes for the fastening screws is shown in the dimensioned drawing. The fastening screws are not
supplied with the machine.
If using anchor bolts, it is necessary to drill holes with a maximum diameter of 40 mm and a maximum
depth of 70 mm. After inserting the bolts, the holes are sealed with plaster or cement mortar.