VOLLMER WERKE
Operating instructions
Issue: 01
MAP 200 / 400
Page: 8-1
8 PREPARATION FOR START UP
8.1 Elements of the machine
1 Frame
2 Blade support
3 Compressed air supply
4 Table with rollers
5 Rail
6 Foot
7 Limit switch
1
2
Only on MAP 400
8.1.1 Installation of the machine
a) Locate the machine frame onto its foundations,
b) Lever the frame with the help of a vertical level gauge.
c) Install the blade supports 2.
d) Put the feet 5 in place.
e) Slip limit switch 7 into rails 6.
f) Join the feet to the frame with the help of rails.
g) Put the table in place with rollers 4.
Note
The operations « d » to « f » are only made on the MAP400.
Note
The frame and the two tables with rollers of the machine are factory set.