<2.Specications>
2-31
IM 11M12G01-02EN 1sh Edition : Mar. 25, 2021-00
To set this, proceed as follows:
pressure, P (at the ejector entrance).
(2) In Graph 1, determine Po (pressure setting) from L (the distance between the ejector and
the pressure gauge).
(3) Open the needle valve to supply air for the ejector to the pressure gauge until it indicates the
pressure setting, Po.
NOTE
"3.2.1 Usage of the High Temperature Probe Adapter (ZO21P-H)" and Section "4.1.4 Piping
to the High Temperature Probe Adapter" for details.
Graph explanation
(1) Graph 1 is to compensate for pressure loss in piping between the ejector and the pressure
(2) Graph 2 shows correlation between P (drive pressure) and Qa (air consumption).
sample gas inlet of the ejector is closed).
(4)