About this manual
23
Installation and commissioning flowchart
Task See
Plan the installation.
Check the ambient conditions, ratings, required
cooling air flow, input power connection, compatibility
of the motor, motor connection, and other technical
data.
Select the cables.
Technical data
Planning the electrical installation
Option manuals (if optional equipment is
included)
Unpack and check the units.
Check the type code indicated by the type
designation label with the original order.
If the drive is about to be connected to an IT
(ungrounded) system:
• check that the drive is not equipped with EMC/RFI
filtering +E202
• if the drive is of frame size R6, check that the drive
is not equipped with EMC/RFI filtering +E200.
Check that all necessary optional modules and
equipment are present and correct.
Mechanical installation
The ACS800-17
For instructions on how to disconnect the EMC/
RFI filtering, contact your local ABB
representative.
If the converter has been non-operational for
more than one year, the converter DC link
capacitors need to be reformed. Contact your
local ABB representative for more information.
Only intact units may be started up.
Check the installation site. Mechanical installation, Technical data
Route the cables. Planning the electrical installation: Routing the
cables
Mount the cabinet line-up. Mechanical installation
Check the insulation of the motor and the motor
cable.
Electrical installation: Checking the insulation of
the assembly
Connect the power cables. Connect the control and
the auxiliary control cables.
Mechanical installation, Planning the electrical
installation, Electrical installation
Check the installation. Installation checklist and start-up
Commission the drive. Installation checklist and start-up, The ACS800-
17, and appropriate firmware manual