Installation and commissioning flowchart
Task See
Plan the installation.
Check the ambient conditions, ratings, required
cooling air flow, input power connection, compatibility
of the motor, motor connection, and other technical
data.
Select the cables.
Planning the cabinet assembly (page 23)
Planning the electrical installation (page 37)
Technical data (page 71)
Option manual (if optional equipment is
included)
Unpack and check the units.
Check that all necessary optional modules and
equipment are present and correct.
Only intact units may be started up.
Mechanical installation: Contents of the
package (page 29)
If the converter has been non-operational for
more than one year, the converter DC link
capacitors need to be reformed. Ask ABB for
more information.
Check the installation site. Mechanical installation: Before installation
(page 30)
Technical data (page 71)
If the drive is about to be connected to an IT
(ungrounded) or corner-grounded system, check that
the internal EMC filtering of the drive has been
disconnected.
Safety instructions: Installation and
maintenance work (page 6)
Install the drive in a cabinet. Mechanical installation: Installation procedure
(page 30)
Route the cables. Planning the electrical installation: Routing the
cables (page 45)
Check the insulation of the supply cable, the motor
and the motor cable, and the resistor cable (if
present).
Electrical installation: Checking the insulation of
the assembly (page 48)