Assembly
Assembly Instructions
18
1HSB435410-2 enrev1
4.9 Assembling the pull-rods
Each pole is supplied set to a basic setting. Adjust the poles to the correct open
position when fitting the operating rod between the operating mechanism and the
poles.
Pull-rod assembly takes place in stages:
Preparations for assembling the pull-rods.
Assembling the pull-rods between the operating mechanism and the poles.
Assembling the pull-rods between the poles.
4.9.1 Preparations for assembling the pull-rods
Check that the closing arm’s (1) locking lug rests against the closing latch
roller (2).
Figure 4-12. Checking of the closing arm’s locking lug.
Adjust the operating mechanism as set out in Figure 4-13. Press down the
locking lug (1) on the operating lever by inserting a tool, for example, a large
screwdriver in the hole (2). Insert a screwdriver in hole (3) and press the
operating lever to the right.
Figure 4-13. Adjusting the operating mechanism.
2
1
B10013
2
3
B10035
3
1
2