Rockwell Automation Publication 825-UM004D-EN-P - November 2012 185
Firmware Upgrade Instructions Chapter 13
d. Enter Access Level 2.
e. Issue STATUS comm
and, and verify that the relay status is OK.
f. Set the relay clock and calendar using the DATE an
d TIME commands.
g. Set the Relay and Port settings using the following commands: SET,
SET M, and SET P.
h. Set the relay passwords with the PA
S co
mmand.
10. Set the communications software settings (baud rate, number of data bits,
nu
mber of stop bits) to agree with the port settings of the 825-P.
11. Issue the STATUS comm
and, and then verify that all relay self-test results
are OK.
12. A
pply current and voltage signals to the relay.
13. Issue the METER c
ommand, and then verify that the current and voltage
signals are correct.
The relay is now ready for your commissioning procedure.