DISTRIBUTION SYSTEMS - ELECTRICA L POWE R SYSTEM
N°
Te st Point Expected Result
Other Result (Possible Cause)
8
Turn the key switch to the ON
position. Turn the Front Electric
ControlSwitchNo. 3totheDOWN
position.
Terminal for wire 007BT to ground.
12 volts
Check the circuit between the loader
lift arm auxiliary electric co nn ector
and the front electric control switch
No. 3. Also check the front electric
control switch No. 3.
9
Turn the key switch to the ON
position. Turn the Front Electric
ControlSwitchNo. 4totheON
position.
Terminal for wire 008B to ground.
12 volts
Check the circuit between the loader
lift arm auxiliary electric co nn ector
and the front electric control switch
No. 4. Also check the front electric
control switch No. 4.
1 04/05/2005
A.30.A / 104