A-14
Cisco Nexus 7000 Series Hardware Installation and Reference Guide
OL-23069-06
Appendix A Technical Specifications
Chassis Clearances
Figure A-13 Power Connector for the 6.0-kW DC Power Supply Unit
Chassis Clearances
You must provide adequate clearance for installing the switch, replacing switch modules, routing cables,
and allowing airflow to and from the switch.
This section includes the following topics:
Cisco Nexus 7009 Chassis Clearances, page A-14
Cisco Nexus 7010 Chassis Clearances, page A-15
Cisco Nexus 7018 Chassis Clearances, page A-15
Cisco Nexus 7009 Chassis Clearances
The Cisco Nexus 7009 chassis requires the following clearances:
If you are using a four-post rack or cabinet, you must have 7 inches (17.8 cm) between the chassis
and the front and back of a four-post rack or interior of the cabinet (required for cabling). This
requirement does not apply to a two-post rack.
Table A-14 6-kW DC Power Supply Power Cord
Locale Part Number Cord Rating Power Cord Reference Illustration
All N7K-DC-CAB 40 A, 48V-48V Figure A-13