5.1.3 Side-by-Side Installation
The frequency converter can be mounted side-by-side and requires the clearance above and below for cooling.
Power [kW] Clearance above/below [mm/inch]
Frame IP class 3x200-240 V 3x380-480 V 3x525-600 V
H1 IP20 0.25-1.5 0.37-1.5 100/4
H2 IP20 2.2 2.2-4 100/4
H3 IP20 3.7 5.5-7.5 100/4
H4 IP20 5.5-7.5 11-15 100/4
H5 IP20 11 18.5-22 100/4
H6 IP20 15-18.5 30-45 18.5-30 200/7.9
H7 IP20 22-30 55-75 37-55 200/7.9
H8 IP20 37-45 90 75-90 225/8.9
H9 IP20 2.2-7.5 100/4
H10 IP20 11-15 200/7.9
Table 5.4 Clearance
NOTICE
With IP21/Nema Type1 option kit mounted, a distance of 50 mm between the units is required.
5.1.4 Field Mounting
IP21/TYPE 1 kits are recommended.