JT5 Operators Manual Conduct a Bore - 81
Assemble Backream String
CMW
®
1. Select backreaming devices. See “Backreamers” on page 104.
2. Determine fluid rate requirements and install appropriate nozzles to provide sufficient flow. See
“Backream Fluid Requirements” on page 105 and “Nozzles” on page 102.
3. Attach backreamer to backream beacon housing if tracking backream.
4. Install beacon, following beacon instructions for:
battery replacement
beacon positioning
5. Install beacon housing lid. See “Beacon Housings” on page 103.
6. Follow beacon instructions to check beacon operation.
7. Follow tracker instructions to calibrate beacon.
8. Connect EZ-Connect joint or use quick wrench to attach backreamer/beacon housing assembly to
transition sub. See “Quick Wrench” on page 107.
9. Attach pullback devices or product to end of backreamer/beacon housing assembly.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Ditch Witch JT5 and is the answer not in the manual?

Ditch Witch JT5 Specifications

General IconGeneral
BrandDitch Witch
ModelJT5
CategoryConstruction Equipment
LanguageEnglish

Related product manuals