DOD Technologies, INC • 675 Industrial Dr. Bldg. A • Cary, IL 60013 • Phone (815) 788-5200 • Fax (815) 788-5300
Vibration Damage and Wire Inspection:
Vibration Damage Inspection Procedure:
The pump panel wiring and tubing (see image below) should be checked periodically for damage caused
by vibration from the pumps. The wiring harnesses and tubing are tied away from vibration before the
CL96 leaves the factory but because the pump panel can be shifted forward the moving parts may not
always lay in the intended position. All of the wiring and pump tubing should be carefully inspected for
holes that could be cause by vibration.
Wire Inspection Procedure:
The wiring throughout the system should be visually inspected and all terminal block jumpers should be
tightened to avoid any intermittent connections. The terminal block jumpers are located in the control
box and on the pump panel on all of the terminal blocks.