56 Eaton 9355 UPS (10/15 kVA) User’s Guide 164201594—Rev H0
Figure 41. Version 2 Bypass Cabinet Bypass AC Input Wiring
20. Verify the phase rotation for each UPS and the bypass input.
21. Reinstall the internal cover.
22. Reinstall the bypass cabinet front cover.
23. Proceed to 4.4 Stabilizing the Cabinet to complete the UPS installation.
44..44 SSttaabbiilliizziinngg tthhee CCaabbiinneett
NOTE 1 For seismic installations, you MUST order and install an Eaton 9355 UPS seismic kit; do
not use the following instructions.
NOTE 2 For non-seismic installations, you MUST install the stabilizing bracket on all 3-high
cabinets. The stabilizing bracket is optional for 2-high cabinets.
To stabilize the cabinet(s):
1. Lower the leveling feet to prevent the cabinet from rolling.
UPS System Installation