EasyManua.ls Logo

Fike Quadnet - Loop Continuity and Insulation Test Results

Fike Quadnet
74 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Quadnet Control Panel Engineering and Commissioning Manual
66
Loop Continuity and Insulation Test Results
After installation of the cable, and termination into all the relevant back-boxes, ensure that the link pins are
installed as necessary in order to be able to take cable continuity and insulation readings. Make sure that all
the cables are dressed smoothly and neatly into their back-boxes in order that they will not be disturbed
after the readings are taken.
The commissioning engineer will require these readings, along with correctly marked ‘as-wired’ drawings
and completed configuration sheets, before attending site to commission the system.
CORE
CONTINUITY READING (OHMS)
LOOP 1
LOOP 2
LOOP 3
LOOP 4
LE1 +ve to LE2 +ve
LE1 -ve to LE2 ve
LE1 Scrn to LE2 Scrn
A reading of approximately 1.2 ohm per 100 metres of 1.5 mm
2
cable is expected and any significant
variation from this should be investigated. If the above readings are satisfactorily showing circuit continuity
then you may also take the reading below.
CORE
CONTINUITY READING (OHMS)
LOOP 1
LOOP 2
LOOP 3
LOOP 4
+ve to -ve
+ve to Screen
-ve to Screen
Loop Screen to Mains
Earth
No continuity between cores should be seen and a reading of OL should be shown on the test meter. Any
significant variation from this should be investigated. If the readings are satisfactory then the loop wiring is
largely proven other than for faults such as complete polarity reversal.
Site Name & Address:
Installation Company:
Testing Engineer:
Signature:
Date:

Table of Contents

Other manuals for Fike Quadnet

Related product manuals