Quadnet Control Panel Engineering and Commissioning Manual
Loop Continuity and Insulation Test Results
After installation of the cable, and termination into all the relevant back-boxes, ensure that the link pins are
installed as necessary in order to be able to take cable continuity and insulation readings. Make sure that all
the cables are dressed smoothly and neatly into their back-boxes in order that they will not be disturbed
after the readings are taken.
The commissioning engineer will require these readings, along with correctly marked ‘as-wired’ drawings
and completed configuration sheets, before attending site to commission the system.
CONTINUITY READING (OHMS)
A reading of approximately 1.2 ohm per 100 metres of 1.5 mm
2
cable is expected and any significant
variation from this should be investigated. If the above readings are satisfactorily showing circuit continuity
then you may also take the reading below.
CONTINUITY READING (OHMS)
Earth
No continuity between cores should be seen and a reading of OL should be shown on the test meter. Any
significant variation from this should be investigated. If the readings are satisfactory then the loop wiring is
largely proven other than for faults such as complete polarity reversal.