This active control will allow the engineer to view or change the
operation of the remote fire event set for programmable input 2. Use
the UP and DOWN arrow keys to toggle through the following options.
To confirm the changes press ENTER.
1. REMOTE FIRE FULL – Operation of I/P 2 will signal a
remote fire at the control
panel. All sounders and relays
will operate.
2. REMOTE FIRE NO RELAYS – Operation of I/P 2 will signal a
remote fire at the control
panel and only the sounders
will operate.
This active control will allow the engineer to view or change the
operation of the technical event set for programmable input 2. Use the
UP and DOWN arrow keys to toggle through the following options. To
confirm the changes press ENTER.
1. LATCH – Operation of I/P 2 will signal a
technical event at the control
panel. All outputs will trigger
and the panel will latch into
fire.
2. NON-LATCH – Operation of I/P 2 will signal a
technical event at the control
panel. All outputs will trigger
for as long as the input is
activated.
This active control will allow the engineer to view or change the
operation of the disablement event set for programmable input 2. Use
the UP and DOWN arrow keys to toggle through the following options.
To confirm the changes press ENTER.
1. DISABLE SOUNDERS – Operation of I/P 2 will disable
the sounders.
2. DISABLE REM.FIRE – Operation of I/P 2 will disable
all remote fire signals.
3. DIS SNDRS/REM FIRE – Operation of I/P 2 will disable
all sounders and remote fire
signals.
4. DISABLE BUZZER – Operation of I/P 2 will disable
all remote fire signals.