Chapter 3 - - Installation Guide Page 37
Chapter 3 - Installation Guide
The primary tasks are designed to be performed in sequence. Follow the sequence of tasks
described for each primary task in Chapter 3 - that follow.
There are marks on the installation steps which are only suitable for fixed RAD system.
Section 1.0
Steps for system installation
1 Complete Pre-Installation Checklist People Required: 1 Minutes to Complete: 10
Fill out the Pre-Installation Checklist to confirm completion of pre-install activities before beginning the
installation process.
2 Target System Identification And Check People Required: 1 Minutes to Complete: 30
Identify and Check Target System
3 Receive and Inventory System People Required: 1 Minutes to Complete: 5
Inventory equipment & report discrepancies immediately.
Collect Product Locator Cards and store in a secure location.
Plan route and transport equipment to room.
4 Control Room People Required: 1 Minutes to Complete: 5
Control Room Placement
5 MIS Cable Connections People Required: 1 Minutes to Complete: 5
Connect MIS Cable
6 AP Assembly Preparation (Fixed RAD system only) People Required: 1 Minutes to Complete: 5
* AP Connection and Placement
7 Detector Installation People Required: 1 Minutes to Complete: 5
Table Upgrade
Wallstand Upgrade
8 System Power Up People Required: 1 Minutes to Complete: 5
System power up
9 Software Configuration People Required: 1 Minutes to Complete: 30
System Software Configuration (site, general, options, upgrade configuration, in-house service, PNF,
HIPAA, monitor setting, OM CBT,DICOM servers, bar code reader, insite.)
AP Configuration
10 Detector Association People Required: 1 Minutes to Complete: 5
Detector Registration
11 AP Assembly Installation People Required: 1 Minutes to Complete: 20
12 Calibration People Required: 1 Minutes to Complete: 20
Complete System Calibration: Detector Size Cal, Detector Cal, PACS/Image Display Test Image
13 QAP People Required: 1 Minutes to Complete: 15
Perform QAP
14 Function Check People Required: 1 Minutes to Complete: 50