GE HEALTHCARE
DIRECTION 5461425-8EN, REVISION 6 BRIVO XR118 SERVICE MANUAL
Page 40 Section 2.0 - Installation Handoff Checklist
General Completed
1.) Walls and floor clear of all obstructions?
2.) Walls finished?
3.) Finished floor installed?
4.) Room lights installed?
5.) Dust-creating work completed?
6.) Old equipment within room removed?
7.) Component positions clearly marked on floor?
8.) Space available to store equipment?
9.) Lock on door, or locked room available?
10.) Room IP Addresses for DICOM and Broadband identified?
11.) Broadband connection provided for InSite connection?
12.) Have all fire/safety inspections for occupancy been completed?
13.) Send completed checklist to the GE Healthcare installation team.
Comments:
Inspection Date(s):
Installation Project Manager Signature